CB Climbing System together with TRIO utilised to jump the cores ahead of the construction of the floors

Waterside Reach
Tonbridge, United Kingdom

Residential apartments of 5-7 Storeys.

Project completed early due to jump form construction.

 

 

 

Location
Main Application
Multistorey & Residential

The Project

   

Project Information

Contracts Manager
Contracts Manager
Tony Lyons
Contracts Manager
The collaboration with PERI was extremely successful and we were delighted to complete the project ahead of schedule. The use of PERI equipment allowed a seamless project and the expertise and vision from the PERI team meant we received the most efficient use of formwork systems.